ActiveSample Project
Sample Kitchen Remodel
Southern California · Kitchen remodel · 6 weeks
This week
6 tasks · 2 subcontractors · inspection Friday- Mon Rough plumbing — sink and dishwasherComplete
Ramos Plumbing (sub)
- Tue Rough electrical — lights and circuitsIn progress
Brightline Electric (sub)
✓ Materials ready (2)
- Tue Blocking for upper cabinetsIn progress
Alberto, Matt
✓ Materials ready (2)
- Wed Cabinet deliveryDelivery
Alberto
- Thu Nail plates and inspection prepPlanned
Matt
⚠ Materials not ready: Nail plates
After: Rough plumbing, rough electrical
- Fri Rough inspection — 9:00 AMInspection
After: Rough plumbing, rough electrical, blocking
Upcoming
- Drywall patch, tape and finish · Next Mon–Wed · after Rough inspection
- Prime and paint · Next Thu · after Drywall
- Install cabinets · Next Fri · after Paint
- Countertop template · Week 4 · after Cabinets
- Countertop fabrication (shop) · Week 4–5 · after Template
- Countertop install and backsplash tile · Week 5 · after Fabrication
- LVP flooring · Week 5 · after Tile
- Finish plumbing, electrical and appliances · Week 6 · after Countertops
- Final inspection and punch list · Week 6 · after Finish work
Built-in sequencing: rough-in → inspection → drywall, cabinets → countertop template → fabrication → install. Move one task and BuildProfit shows what has to move with it.